Which surface preparation method reduces structural capacity?

Prepare for the SCDOT Asphalt Roadway Technician Exam. Use flashcards and multiple choice questions with clear hints and explanations. Excel in your exam preparation!

Multiple Choice

Which surface preparation method reduces structural capacity?

Explanation:
Removing material from the pavement’s structural section is what changes its ability to carry loads. Cold milling shaves off pavement with a drum, and it can remove beyond just the surface into the underlying base. This reduces the remaining structural capacity until a new layer is placed to restore it. In contrast, planing and asphalt milling mainly take off the top layer while leaving most of the base and subbase intact, so the structural capacity isn’t reduced as much. Adding a PCC overlay actually increases capacity by putting a new concrete layer on top. So the method that reduces structural capacity the most is cold milling.

Removing material from the pavement’s structural section is what changes its ability to carry loads. Cold milling shaves off pavement with a drum, and it can remove beyond just the surface into the underlying base. This reduces the remaining structural capacity until a new layer is placed to restore it. In contrast, planing and asphalt milling mainly take off the top layer while leaving most of the base and subbase intact, so the structural capacity isn’t reduced as much. Adding a PCC overlay actually increases capacity by putting a new concrete layer on top. So the method that reduces structural capacity the most is cold milling.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy